Progress Reporting

~ By Duncan Haughey

Green arrows reading progress

Progress reporting is an essential activity of project management. The project manager issues regular reports on progress against budget, schedule and scope. Include these people on your circulation list:

  • Project Sponsor
  • Budget Holder
  • Senior Users
  • Team Members

Keep the report brief and sum up the key points in your project. I recommend this simple format on a maximum of two pages:

  1. Report Date
  2. Overall Status
  3. Project Summary
  4. Key Issues
  5. Identified Risks
  6. Tasks and Next Steps
  7. Decisions Needed
  8. Key Future Dates
  9. Budgeted Cost
  10. Spend to Date

Anyone reading the report must be made aware of progress and know when their help is needed to keep the project on track.

Keeping people updated ensures they remain involved and committed. Regular communication is essential to the well-being of any project. Common failings in this area are:

  • Poor communication channels
  • Lack of honest communication
  • Unwillingness to communicate bad news
  • Not asking for help if it's needed

Regular progress reporting creates a valuable written record of a projects' life. Later you can look back and decide how to improve the running of future projects.


Enjoyed this article? Now read 21 Ways to Excel at Project Management


Comments

Be the first to comment on this article.

Add a comment



(never displayed)



 
2000
Is it true or false that green is a number?
Notify me of new comments via email.
Remember my form inputs on this computer.

Top 10 Qualities of an Excellent Manager

The word excellent on a virtual interface with a businessman standing behind it

What are the most important qualities of an excellent manager that allows them to tap into talents and resources in order to support and bring out the best in others.

Managing The Project Time

Man pointing at an alarm clock

Project managers should know the iron triangle of project management, sometimes called the triple constraints of project management, because all projects are constrained by these elements.

How to Become a Project Manager

Senior lecturer in front of his class

If you're new to project management don't be bamboozled by all the jargon. This article sets out the skills needed to become a competent project manager.

How Agile Practices Reduce Requirements Risks

Road warning sign - Risks Ahead

Every software project carries some risk, but many of these risks can be mitigated. That's true of problems related to product requirements.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Robbie Rowland commented on…
Better Coaching Using the GROW Model
- Tue 28 March 12:01am

Velma Tailly commented on…
Better Coaching Using the GROW Model
- Sat 25 March 7:23pm

Joseph Marandus commented on…
How to Apply PRINCE2: Engaging Senior Management in Your Projects
- Tue 21 March 1:59pm

Latest tweets

General Project Management • Re: How do you track who from your human resources have related… https://t.co/GQfwuFRDQP #projectsmart #pmot about 2 days ago

General Project Management • How to gain experience in Project Management? https://t.co/hsWb5YUKei #projectsmart #pmot about 2 days ago

General Project Management • No Sponsor https://t.co/ii52CgAiCs #projectsmart #pmot about 13 days ago