How to Implement Earned Value

~ By Kay Wais

A plant growing between coins in a mans hands

Earned Value (EV) is one of the most sophisticated and accurate methods for measuring and controlling project schedules and budgets. Earned value has been used extensively in large projects, especially in government projects. PMI is a strong supporter of the Earned Value approach because of its ability to accurately monitor the schedule and cost variances for complex projects.

Although it is sophisticated, Earned Value can be scaled to be appropriate for any size of project. The key is in the project planning.

There are three primary advantages to using Earned Value:

  1. Accuracy in reporting
  2. Ability to deal with the uneven rate of project expenditures and work
  3. The early warning it provides project managers, allowing them to take the necessary corrective action should the project be spending more money than it is physically accomplishing

Other less professional methods for measuring budget and schedules generally only monitor the percent of the time through the schedule and make the often mistaken assumption that this is also the percent that the project should be through the budget. But cost and project progress generally are not evenly expended through a project. The reason Earned Value stands above the alternatives is that it accurately deals with this reality. Earned Value warning signals become available to management as early as 15 to 20 percent into a new project, in ample time to take corrective measures.

How to Implement Earned Value

In order to employ Earned Value, we must have a baseline plan (including a detailed, workload levelled, progress schedule) in place that will allow us to continuously measure seven points of data. The textbooks, including the referenced ones at the end of this paper, say that this is easy. However in my reality it often is not easy because scheduling to this level of detail at the beginning of the project is challenging and dynamic.

Earned Value requires the kind of data most projects have, but we may not look at the data in quite the same way. Earned Value has a focus on its percent-complete position…against its (100 percent) defined scope.

In order to employ Earned Value we must first know at all times what the "planned value" is as at any point in time. So Earned Value is built on a very structured project plan. It requires a detailed WBS, time and cost estimates for all of the work packages, a workload levelled master schedule, and a meticulous change management methodology (with this last part being the hardest for my projects).

To determine the planned value, we need to calculate two important base factors, 1) how much physical or intellectual work we have scheduled to be completed as of the point of measurement, and 2) what was the budgeted value of the work scheduled.

To measure Earned Value we need two new points of data: 3) how much of our scheduled work have we actually accomplished? And 4) what is the budgeted value of the work actually performed?

The next item is for the Earned Value work we have accomplished, what 5) costs have we actually spent and/or incurred.

The Planned Value = Items 1 and 2
The Earned Value = Items 3 and 4
Actual Costs = 5

Next we need to understand 6) the "schedule variance" which in Earned Value is the difference between our planned value scheduled and our Earned Value achieved. Lastly, we need to know 7) what our "cost variances" have been. This is determined by relating our Earned Value accomplished against the actual costs pent or incurred.

These are the basics. There are many calculation tables, charts, at graphs that can help visual display this data, variances, and trends. These are frosting on the cake and not necessary to use Earned Value. Earned Value summary reports often will provide a revised estimate to complete based on the extension of the current trends.

Summary

Implementing Earned Value is well worth the effort. The advantages of building a detailed plan, controlling and monitoring the project, and accurate reporting and forecasting are all critical to professional project management.

The biggest challenge our company experienced when implementing Earned Value was changing our time reporting and accounting system to decompose projects, allowing time and cost to be attributed to specific project deliverables. Also, as mentioned earlier, the detailed schedule must be planned early and translated to project costs - to give us the planned value at any specific point in time.

Once armed with the Earned Value information, the project manager and stakeholders can truly understand the current status of a project, the rates of variances, and (once significantly into the project) often accurately predict the end schedule and budget compared to the original estimates.


References and Resources

Fleming, Quentin and Koppelman, Joel from Primavera Systems. Earned Value Project Management … an Introduction (PDF)

Fleming, Quentin and Koppelman, Joel, Earned Value Project Management, Second Edition (Kay read this book in Feb. of 2001)

Milosevic, Dragan, Project Management Toolbox, ISBN 0-471-20822-1, Wiley Press. 2003


Successful Projects is a project management training company in La Crosse, Wisconsin. Successful Projects can be found at http://www.successfulprojects.com


Comments

Be the first to comment on this article.

Add a comment



(never displayed)



 
2000
What is the fifth month of the year?
Notify me of new comments via email.
Remember my form inputs on this computer.

Project Management Maturity Model

Five maturity levels concept

The concept of a project management maturity model has evolved considerably from the software industry. Where does your organisation sit on the maturity model?

Four Steps to Project Time Management

Man pointing at an alarm clock

The four steps outlined in this article will help you better define and measure the activities that make up your project timeline.

How to Build a High-Performance Project Team

Business people and bar graph going upwards

What makes a winning project team? Why do some teams achieve greatness while others struggle? Let's look at the factors present on winning project teams.

Effort Estimating: A Primer

Effort time money blue dice representing the ingredients for business

Good estimating is a skill like any other, it can be developed with practice to the point where it may seem like magic to the uninformed.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Allana commented on…
12 Tips for Being a Good Manager
- Tue 5 January 8:30pm

George Bockius commented on…
Better Coaching Using the GROW Model
- Thu 24 December 3:55pm

Al commented on…
Better Coaching Using the GROW Model
- Tue 22 December 10:07pm

Latest tweets

General Project Management • IT project management phrases - 10 terms you need to know https://t.co/0ThVkIz5JU https://t.co/AqimD0V75x about 1 day ago

General Project Management • An Optimist's View Going into 2021 https://t.co/E8b4eh3wXr about 5 days ago

An Optimist's View Going Into 2021 by Simon Sinek https://t.co/1iRNMfYlUo An inspiring read to help you start 2021… https://t.co/xm5ZI4jBr5 about 9 days ago