Project Smart ~ Exploring trends and developments in project management today

Calendar iconNot recorded
Adobe PDF icon

How Gantt Charts Can Help Avoid Disaster

~ By Linda Russell

Gantt chart

Having run fifteen months late on completion of a construction project, a building company incurred extensive penalty charges, which eventually led to its closure. Not having any project Gantt charts indirectly led to the company's failure.

Background

In my article Gantt Charts, Pert Charts: What Use are They? I said that Gantt charts are useful tools to help you manage better, but they won't give you all the answers. What I didn't say is that not having a Gantt chart can be disastrous: a company recently went into receivership, partly because it didn't have Gantt charts showing the critical paths on a major construction project.

Penalty Charges

The original contract for the construction of a block of flats did not include a dated project plan showing the critical path. When changes to the specification were made by the customer, no plan revisions could be produced to show how these changes would affect the project end date. The flats were finally ready for handover some fifteen months later than the original agreed end date, leading to penalty charges.

In order to contest the penalty charges, the company needed to show:

  1. The handover date specified in the contract was possible within the original specification
  2. That the end date was bound to slip because of the extra tasks and extended durations caused by the customer's changes

All they had was a series of spreadsheets listing the tasks undertaken: a new spreadsheet was created when each change was made. The spreadsheets didn't show the variances from the original plan, nor what the impact of those changes was on the project dates.

How Gantt Charts Would Have Helped

If they had created a Gantt chart at the contract stage, they would have had a baseline plan against which they could monitor their progress.

When the customer requested amendments to the specification, the company could have added in the necessary extra tasks and changed the durations of the existing tasks as required: this would have clearly shown the handover date slippage. The customer could then have been called upon to sign an amendment to contract, agreeing a revised end date.

Without these tools, the company was unable to prove that the delay was not caused by their own inefficiencies, although it could be argued that trying to manage a complex construction project without using appropriate planning tools is an indication of inefficiency in itself.

Conclusion

If you are called upon to manage a project for a customer where time is of the essence, you need to use appropriate tools, such as Gantt charts, to monitor the plan and work out the impact of changed circumstances, and communicate the changes to all concerned.


Linda Russell has an M.A. (with Distinction) in Technical Authorship, and over 25 years' experience in software implementation and consultancy.


Comments (1)

Topic: How Gantt Charts Can Help Avoid Disaster
5/5 (1)
Gravatar
Full StarFull StarFull StarFull StarFull Star
1st March 2017 9:34am
Ahmad (Manama) says...
Using PMI guidelines, supporting tools, process and techniques are always a safeguard against any risk in project management.

Add a comment



(never displayed)



 
2000
Enter the third word of this sentence.
Notify me of new comments via email.
Remember my form inputs on this computer.

12 Tips for Being a Good Manager

Businessman revealing the inner superhero

Keeping a project management team running smoothly can be a challenge, especially when budgets are lean and expectations are high.

Rolling Wave Planning

Blue rolling wave

What is rolling wave planning and how does it affect the critical chain? This article by John Goodpasture provides a detailed explanation.

Top 10 Benefits to Earning a Certification

University students in a classroom watching a presentation

Is it worth putting in all of the work? Consider these benefits of earning a certification, and if you see the benefits for your situation, go for it!

Agile Through the Waterfall

Agile and waterfall tag cloud

Many organisations have adopted Agile practices into their development methodologies and they have proved to be successful for the organisation as a whole.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Allana commented on…
12 Tips for Being a Good Manager
- Tue 5 January 8:30pm

George Bockius commented on…
Better Coaching Using the GROW Model
- Thu 24 December 3:55pm

Al commented on…
Better Coaching Using the GROW Model
- Tue 22 December 10:07pm

Latest tweets

General Project Management • IT project management phrases - 10 terms you need to know https://t.co/0ThVkIz5JU https://t.co/AqimD0V75x about 13 hours ago

General Project Management • An Optimist's View Going into 2021 https://t.co/E8b4eh3wXr about 4 days ago

An Optimist's View Going Into 2021 by Simon Sinek https://t.co/1iRNMfYlUo An inspiring read to help you start 2021… https://t.co/xm5ZI4jBr5 about 9 days ago