Project Smart ~ Exploring trends and developments in project management today

Calendar iconNot recorded
Adobe PDF icon

How Gantt Charts Can Help Avoid Disaster

~ By Linda Russell

Gantt chart

Having run fifteen months late on completion of a construction project, a building company incurred extensive penalty charges, which eventually led to its closure. Not having any project Gantt charts indirectly led to the company's failure.

Background

In my article Gantt Charts, Pert Charts: What Use are They? I said that Gantt charts are useful tools to help you manage better, but they won't give you all the answers. What I didn't say is that not having a Gantt chart can be disastrous: a company recently went into receivership, partly because it didn't have Gantt charts showing the critical paths on a major construction project.

Penalty Charges

The original contract for the construction of a block of flats did not include a dated project plan showing the critical path. When changes to the specification were made by the customer, no plan revisions could be produced to show how these changes would affect the project end date. The flats were finally ready for handover some fifteen months later than the original agreed end date, leading to penalty charges.

In order to contest the penalty charges, the company needed to show:

  1. The handover date specified in the contract was possible within the original specification
  2. That the end date was bound to slip because of the extra tasks and extended durations caused by the customer's changes

All they had was a series of spreadsheets listing the tasks undertaken: a new spreadsheet was created when each change was made. The spreadsheets didn't show the variances from the original plan, nor what the impact of those changes was on the project dates.

How Gantt Charts Would Have Helped

If they had created a Gantt chart at the contract stage, they would have had a baseline plan against which they could monitor their progress.

When the customer requested amendments to the specification, the company could have added in the necessary extra tasks and changed the durations of the existing tasks as required: this would have clearly shown the handover date slippage. The customer could then have been called upon to sign an amendment to contract, agreeing a revised end date.

Without these tools, the company was unable to prove that the delay was not caused by their own inefficiencies, although it could be argued that trying to manage a complex construction project without using appropriate planning tools is an indication of inefficiency in itself.

Conclusion

If you are called upon to manage a project for a customer where time is of the essence, you need to use appropriate tools, such as Gantt charts, to monitor the plan and work out the impact of changed circumstances, and communicate the changes to all concerned.


Linda Russell has an M.A. (with Distinction) in Technical Authorship, and over 25 years' experience in software implementation and consultancy.


Comments (1)

Topic: How Gantt Charts Can Help Avoid Disaster
5/5 (1)
Gravatar
Full StarFull StarFull StarFull StarFull Star
1st March 2017 9:34am
Ahmad (Manama) says...
Using PMI guidelines, supporting tools, process and techniques are always a safeguard against any risk in project management.

Add a comment



(never displayed)



 
2000
Enter the last letter of the word model.
Notify me of new comments via email.
Remember my form inputs on this computer.

The Meat of a Business Case

Abstract word cloud for Business case with related tags and terms

Writing a business case is a crucial component in the business process. This article covers the important components in a business case.

Managing The Project Time

Man pointing at an alarm clock

Project managers should know the iron triangle of project management, sometimes called the triple constraints of project management, because all projects are constrained by these elements.

Building Teamwork

Business colleagues arranging multicoloured labels on a meeting table

Teamwork isn't something that just happens. The project leader needs to put in the time and effort to build the team and help everyone get along. Here's how.

Project Cost Management

Pile of British one pound coins

How do we know what a project will cost? We really don't until the project is complete because we can't accurately predict the future. What we can do is create an estimate.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Duncan Haughey commented on…
Psychology for Project Managers
- Thu 22 October 5:10pm

Michael Fayamba commented on…
RACI Matrix
- Sun 18 October 6:34pm

Muhammed Ayub commented on…
Understanding the Project Management Triple Constraint
- Fri 9 October 8:54am

Latest tweets

General Project Management • Job opportunities as you get older https://t.co/wEbf7foa16 about 1 day ago

General Project Management • Re: Why is it important to develop a product-thinking mindset? https://t.co/jcA2QT4laM about 2 days ago

General Project Management • Why is it important to develop a product-thinking mindset? https://t.co/IUW782zrve about 2 days ago