Query on PMP Numericals

This forum is for members to share and gain knowledge of Project Management. Got a question about project management? Need help with a problem? Wish to offer tips and advice? Post here.
Post Reply
777upender
New Member
New Member
Posts: 1
Joined: Thu 21 Jan 2021 4:48 pm

A project has a budget of Rs.3,00,000 and a planned duration of 24 months.The following table shows progress information for the first four months. Figures are cumulative:

Month 1 2 3 4
Planned (Rs) 20,000 40,000 60,000 90,000
Actual Spend (Rs) 12,000 28,000 50,000 76,000
Earned Value (Rs) 10,000 24,000 42,000 64,000

What is the cost variance and schedule variance at the end of the third month and the estimate at completion based on the 3rd month progress information?

I calculated:
CV - 8000
SV -18000

But, how to estimate at completion based on the 3rd month progress information?