Month | 1 | 2 | 3 | 4 |
Planned (Rs) | 20,000 | 40,000 | 60,000 | 90,000 |
Actual Spend (Rs) | 12,000 | 28,000 | 50,000 | 76,000 |
Earned Value (Rs) | 10,000 | 24,000 | 42,000 | 64,000 |
What is the cost variance and schedule variance at the end of the third month and the estimate at completion based on the 3rd month progress information?
I calculated:
CV - 8000
SV -18000
But, how to estimate at completion based on the 3rd month progress information?