Which Project Phase is HyperCare?

Postby nohams » Sat 06 Oct 2018 8:46 pm

Hello,

Where does HyperCare fit in the project phases (initiating, planning, executing, monitoring and control, closing)? Does it belong to the "Closing" phase? Or, is it outside the project's scope?

Thanks in advance.

User avatar
dhaughey
Site Admin
Site Admin
Posts: 412
Joined: Sat 19 Dec 2009 4:39 pm
Location: London

Re: Which Project Phase is HyperCare?

Postby dhaughey » Sun 07 Oct 2018 9:34 am

Interesting question. Personally, I would have it as part of the project. I would include hypercare and stabilisation in the project plan and handover to the support team to complete the hypercare period before I closed the project.

Ussere
New Member
New Member
Posts: 1
Joined: Mon 19 Nov 2018 10:07 am
Location: https://diceus.com/open-source-erp-java ... ct-choose/

Re: Which Project Phase is HyperCare?

Postby Ussere » Mon 19 Nov 2018 10:28 am

dhaughey wrote:Interesting question. Personally, I would have it as part of the project. I would include hypercare and stabilisation in the project plan and handover to the support team to complete the hypercare period before I closed the project.


Thanks, for this answer!

Stephbaker
Full Member
Full Member
Posts: 8
Joined: Mon 03 Dec 2018 2:16 pm

Re: Which Project Phase is HyperCare?

Postby Stephbaker » Tue 04 Dec 2018 7:29 am

dhaughey wrote:Interesting question. Personally, I would have it as part of the project. I would include hypercare and stabilisation in the project plan and handover to the support team to complete the hypercare period before I closed the project.

Nicely written, sir!