Lessons Learned - Billing

This forum is for members to share and gain knowledge of Project Management. Got a question about project management? Need help with a problem? Wish to offer tips and advice? Post here.
Post Reply
landeau101
New Member
New Member
Posts: 1
Joined: Fri 07 Oct 2016 11:13 pm

I'm new to a consulting firm. When conducting lessons learned, is it appropiate to bill resource time to the client (as part of project). Thank you for your input.
User avatar
dhaughey
Site Admin
Site Admin
Posts: 495
Joined: Sat 19 Dec 2009 4:39 pm
Location: London

If you share the lessons with your customer to help them become more efficient in the future, I would bill them. If it is purely internal to help your organisation perform better in the future, then I would not. It depends on how granular you are with your billing. I usually bill for project management as an item, which includes all elements of managing the project including lessons learned.