Hello All,
I'm studying for PMP and so I'm currently working through an e-learning program describing all of the Process, ITTOs and Activities.
However (for now at least) the chronology of the processes is not at all evident.
Obviously we work through the Process Groups ( I > P > E / M&C > C) left to right, but there is no indication so far of what is best practice within the groups - for example within the planning group some processes appear to be inputs to one another, so what comes first?
I appreciate that there can be variance across different projects but I would certainly find it extremely helpful to see an online lecture or article which took a hypothetical 'typical' project through all 47 processes, with the ITTOs, in the order in which these might occur in reality.
Does anyone know of such a resource, or have any pointers to assist?
Thanks in advance,
Jamie
Chronology of PMBOK Processes and ITTOs Within a Project
-
- New Member
- Posts: 1
- Joined: Sun 05 Jul 2020 1:50 pm
I agree with you, in my humble opinion as a new student of project management here in Europe: the test question 27 page 270 of Mulcahy's book, the answer says that I need a, "preliminary schedule approved by the project team", as an action right after "the WBS, the network diagram and work-package-estimates".
The book says also that an approved preliminary schedule is an input for risk planning, but why I can not find an illustrative diagram or flow process of the whole PMBOK, it is very hard to find those PMBOK processes simulated and organized in a timeline.
I'm sorry for my English.
I hope I find the time to develop myself this timeline with high-detail.
The book says also that an approved preliminary schedule is an input for risk planning, but why I can not find an illustrative diagram or flow process of the whole PMBOK, it is very hard to find those PMBOK processes simulated and organized in a timeline.
I'm sorry for my English.
I hope I find the time to develop myself this timeline with high-detail.