I have a question about the Earned Value Method.
If I am close to finish my project, and I have finished all the activities from the week 1 to week 9, can the curve of planned value be equal than the earned value in the period week 1-9?
Thanks a lot.
PS: Please check my attached file, there is the graphic and metrics.
Earned Value Method
- Attachments
-
- VG(2).xlsx
- Earned Value
- (33.35 KiB) Downloaded 207 times
Hi,
I am going to say yes; assuming that the value actually earned is equal to the planned value. This means you are bang on target and on track to hit BAC (Budget At Completion) as projected.
Also, I not know what week is (semana) in Spanish!
Thanks,
Kit
I am going to say yes; assuming that the value actually earned is equal to the planned value. This means you are bang on target and on track to hit BAC (Budget At Completion) as projected.
Also, I not know what week is (semana) in Spanish!
Thanks,
Kit