Hello,
I have a quick question regarding critical path analysis. Would in the attached picture it will be correct to say that my critical path is = D,E,G,H?
Regards,
Haroon
Critical Path Analysis
Hi
Can anyone help me answer two questions from the diagram that a is attached:
1. What is the critical path of this network diagram? From what I understand critical path are activities with Total Slack=LS-ES=0 and Total Slack=LF-EF=0. But below diagram because of the lag I have different values for the start and finish activity for the slacks. The only activities that satisfy Total Slack=LS-ES=0 and LF-EF=0 are A,C,E, H and J...But I cannot get to J with the critical activities? Please make me understand why...have I missed something here?
2. from the diagram what is the critical path duration? I assume it is 52 days.
Help much appreciated.
Best Rgds
Can anyone help me answer two questions from the diagram that a is attached:
1. What is the critical path of this network diagram? From what I understand critical path are activities with Total Slack=LS-ES=0 and Total Slack=LF-EF=0. But below diagram because of the lag I have different values for the start and finish activity for the slacks. The only activities that satisfy Total Slack=LS-ES=0 and LF-EF=0 are A,C,E, H and J...But I cannot get to J with the critical activities? Please make me understand why...have I missed something here?
2. from the diagram what is the critical path duration? I assume it is 52 days.
Help much appreciated.
Best Rgds
- Attachments
-
- Screen Shot 2016-04-03 at 4.03.18 am.png (142.48 KiB) Viewed 8145 times
Can you please explain in brief about critical path analysis for the examples mentioned. I am quite confused!!