Hi everyone,
In fact I have just started an internship doing project management. It is a project with 4 different sub projects and I want to be able to find the critical path of the whole project using a master schedule. I already know that we can use MSP master schedule, but how can I obtain my critical path?
I appreciate any suggestions.
BR
Multi Project Scheduling
Hi Miladtahanan,
In MSP you can use the filters on the formatting toolbar to show critical path tasks. This will work for a Master Schedule also, but I think you're asking whether you can find the combined critical path of all four projects. I don't think you can. If somebody knows otherwise I'd be interested to hear how it's done.
Duncan
In MSP you can use the filters on the formatting toolbar to show critical path tasks. This will work for a Master Schedule also, but I think you're asking whether you can find the combined critical path of all four projects. I don't think you can. If somebody knows otherwise I'd be interested to hear how it's done.