PMP Exam Tip: Leads, Lags and... Hammocks??

This forum is for members to share and gain knowledge of Project Management. Got a question about project management? Need help with a problem? Wish to offer tips and advice? Post here.
Post Reply
User avatar
cornelius.fichtner
Expert Member
Expert Member
Posts: 103
Joined: Fri 05 Mar 2010 11:19 pm

The terms leads and lags are used to identify and control the timing of various activities within the project. It is important to accurately document leads and lags.

Lead Time: Let's assume a project has two pieces that need to be completed at the same time. Work package A will take 4 weeks to complete, but work package B only takes one week. B would show in the project plan as a finish to start (FS) with a one week lead. This means the B work package component should start one week before A is scheduled to be completed.

Lag Time: Lag time can best be described as a planned or forced delay. A great example of this is a construction project that involves pouring concrete. The project plan must include a lag time of 2 days for the concrete to dry before the next phase can begin.

Hammock Activity: Hammock activity is also frequently referred to as summary activity. These are activities that are roughly related and are reported as a single activity. Some times the relationship between the activities is clear, other times they may only be related because their completion leads to the same result. On a gantt chart a hammock activity is usually displayed as a thick black bar above a grouping of lower level activities.
Until Next Time,
Cornelius Fichtner, PMP