Where does HyperCare fit in the project phases (initiating, planning, executing, monitoring and control, closing)? Does it belong to the "Closing" phase? Or, is it outside the project's scope?
Thanks in advance.
Which Project Phase is HyperCare?
Interesting question. Personally, I would have it as part of the project. I would include hypercare and stabilisation in the project plan and handover to the support team to complete the hypercare period before I closed the project.
-