Which Project Phase is HyperCare?

Moderator: kwalford

nohams
New Member
New Member
Posts: 1
Joined: Sat 06 Oct 2018 8:21 pm

Which Project Phase is HyperCare?

Postby nohams » Sat 06 Oct 2018 8:46 pm

Hello,

Where does HyperCare fit in the project phases (initiating, planning, executing, monitoring and control, closing)? Does it belong to the "Closing" phase? Or, is it outside the project's scope?

Thanks in advance.

User avatar
dhaughey
Site Admin
Site Admin
Posts: 411
Joined: Sat 19 Dec 2009 4:39 pm
Location: London

Re: Which Project Phase is HyperCare?

Postby dhaughey » Sun 07 Oct 2018 9:34 am

Interesting question. Personally, I would have it as part of the project. I would include hypercare and stabilisation in the project plan and handover to the support team to complete the hypercare period before I closed the project.