If the Earliest Finish of the final activity of a network is 20 days then what would the Latest Finish be?
My answer would be it depends on the duration of the final activity of the plan.
Answers please ladies and gents!
What is the answer to this Critical Chain question?
-
- Expert Member
- Posts: 57
- Joined: Thu 20 Sep 2012 10:19 am
- Location: France
Hi,
If the earliest finish of the final activity of a network(the critical chain) is 20 days, the latest finish can be worked out provided the project buffer is made available ahead of the latest finish date which marks the project completion date, therefore your answer would be 20days plus the project buffer.
Regards
Mohamed Bnemerikhi
If the earliest finish of the final activity of a network(the critical chain) is 20 days, the latest finish can be worked out provided the project buffer is made available ahead of the latest finish date which marks the project completion date, therefore your answer would be 20days plus the project buffer.
Regards
Mohamed Bnemerikhi
-
- Expert Member
- Posts: 57
- Joined: Thu 20 Sep 2012 10:19 am
- Location: France
In Critical chain terminology it is called a buffer and represents "aggregate float" I guess.