Search found 3 matches
- Fri 19 Feb 2016 2:20 pm
- Forum: General Project Management
- Topic: Auto Updating Project Plans
- Replies: 2
- Views: 8393
Re: Auto Updating Project Plans
If you are having to update multiple lines due to delays, have you got your dependencies set up correctly? Have you got your initial dates and timescales set up realistically? If you have it set up right, you can change one date and the rest will knock on as a consequence...don't forget to use basel...
- Fri 19 Feb 2016 2:15 pm
- Forum: General Project Management
- Topic: Project Resource Capacity Planning
- Replies: 7
- Views: 28903
Re: Project Resource Capacity Planning
It's not too difficult in MS Project 2010 to set up custom reports if you need to produce the same or updated datasets frequently.
You can also set up the view so that you can see a couple of the resource elements at the same time.
You can also set up the view so that you can see a couple of the resource elements at the same time.
- Fri 19 Feb 2016 2:11 pm
- Forum: General Project Management
- Topic: PRINCE2 - Is it worth it?
- Replies: 9
- Views: 32075
Re: PRINCE2 - Is it worth it?
I have the PRINCE2 Practitioner, and it provides a good framework to manage projects of all shapes and sizes in various industries. In regards to career planning using project management, I have recently used Primavera P6 to plan my engineering HND using the modules as WBS's and correctly resourcing...