How to allocate resources to activities in a project?
I was wondering if there is a known method to allocate resources dynamically to activities. For example, suppose that I have the following workflow: A(2) -> B(3) // C(1) Where A is the first activity, and B and C are activities performed in parallel. The numbers represent the cost of each activity, ...