Search found 1 match

by ProjectManager76
Tue 23 May 2017 6:06 pm
Forum: General Project Management
Topic: Earned Value Management
Replies: 0
Views: 917

Earned Value Management

Hi there, I am trying to wrap my head around using Earned Value Management in practice but I don't know how to calculate Planned Value for activities that cost nothing to the project. Example : High level milestones for a Data centre project to install some new servers into an existing cluster. Mile...