Better Risk Management With PRINCE2

~ By David Hinde

Red flowchart showing risk element

PRINCE2 has always had a solid, but simple way of dealing with risk. With the latest version, released in June, a number of excellent ideas and concepts have been introduced. Here are the best seven:

Step 1: Having a Risk Management Strategy

In my experience risk management is something that is talked about a lot but rarely done. One problem is that people don't know who should be doing what. To help with this PRINCE2 2009 introduces a Risk Management Strategy. It outlines the way in which risk will be identified, evaluated and dealt with in a project. It shows who should be responsible for carrying out the various risk management roles. It also sets out how much risk an organisation is willing to bear. The strategy is put together at the outset of the project; everyone reviews and signs up to it.

Step 2: Risk Identification Techniques

Where do you start when it comes to identifying all the potential risks in your project? The new manual gives a number of approaches. These include reviewing lessons learned from previous projects, carrying out a risk brainstorming session, using an industry specific prompt list showing likely areas of risk or creating a risk breakdown structure. The latter is a hierarchical diagram like an organisation chart. It can be sub-divided in a range of ways, for example by product, by team or using PESTLE (political risks, economic risks, social risk, technological risks, legal risks, environmental risks). It can be used as a focal point for a workshop to identify all risks in each area of the project.

Step 3: Early Warning Indicators

It is all too easy for a project manager to myopically focus on a small set of performance areas such as work completed to schedule. The new manual suggests a range of other early warning indicators that identify how the project is performing. For example percentage of approvals accomplished, number of issues being raised and number of defects being captured in quality inspections. Reviewing all aspects of a project increases the likelihood of identifying more critical risks.

Step 4: Assessing the Overall Risk Exposure

PRINCE2 2009 gives an approach to show the overall risk situation of a project. Each risk is given a likelihood in percentage terms and an impact should it occur in monetary terms. By multiplying one by the other an expected value can be calculated. Totalling the expected values of all the risks gives a monetary figure that easily shows the exposure of the whole project to risk.

Step 5: Considering the Effect of Time on a Risk

PRINCE2 has always recommended recording when each risk will occur. It calls this the proximity of the risk. But in this latest release it gives examples of how you might categorise proximity, such as imminent, in the next stage of the project or after the project. It also recommends considering whether the probability of the risk occurring and/or the impact on the project if they do occur, might vary over time. Having this information can help focus on risks that are of a more pressing concern.

Step 6: Giving a Clearer Approach to Help Define Risks

Rather than just thinking about the event that may or may not occur such as a road collapsing underneath a heavy load, the new manual considers what could cause the event. This allows for a deeper analysis of any individual risk. If the road collapses it could be caused by heavy rain, bad driving or initial poor construction of the road by the council. Understanding what are the most likely causes for each potential risk event, can help implement better mitigation plans to deal with them.

Step 7: Focus on Opportunities

Risks can be opportunities. For example a new technology might appear to speed the programming of a software module. PRINCE2 2009 gives three ways of approaching an opportunity: exploit it by doing something that ensures it occurs, increase the probability or impact of the event occurring or simply reject the opportunity. In practice a good project manager is always looking for opportunities to improve their project, but making this explicitly part of the risk management process, improves the probability of spotting more.


David Hinde is a recognised expert in management development and executive coaching in the UK. He founded Orgtopia in 2003 and since has helped many organisations such as the BBC, Citigroup and the British Army to develop and unlock their leadership and management potential.


Advertisement


Comments

Be the first to comment on this article.

Add a comment



(never displayed)



 
2000
Enter the second letter of the word horse.
Notify me of new comments via email.
Remember my form inputs on this computer.

Managing Small Projects

A project management workflow diagram written on yellow sticky notes

Project management best practices can easily be applied on small projects to enable you to plan and manage your project successfully.

The Four Stages of Recovering a Project

Road sign reading Road to Recovery

If a project is in trouble, the project manager needs to work to recover it and get back on track. Four steps will help the PM facilitate the recovery.

The Most Common Sourcing RFP Mistakes

Manager passing a document to a colleague

Five of the most common mistakes in internally developed RFPs and how companies can better manage these issues by improving their RFP processes.

Effective Project Communications

Business people shaking hands, finishing up a meeting

Communication is something to think about every day. Are your messages clear? Have you provided enough context? Are your expectations for any outcome apparent?

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Ashwini Pendharkar commented on…
10 Golden Rules of Project Risk Management
- Tue 20 June 1:32pm

Tery commented on…
A Brief History of SMART Goals
- Mon 19 June 10:10pm

Tammy Marin commented on…
Better Coaching Using the GROW Model
- Thu 15 June 10:37pm

Latest tweets

General Project Management • Please Advise: Does PRINCE2 Practitioner Exam Scenerio Changes… https://t.co/OK90gkJzMN #projectsmart #pmot about 12 days ago

RT @rkelly976: “I cannot give you the formula for success, but I can give you the formula for failure, which is: Try to please everybody.”… about 14 days ago

General Project Management • Re: Do I need project management software? https://t.co/u4Tu1fnzuY #projectsmart #pmot about 14 days ago