~ By David Hinde

Red flowchart showing risk element

PRINCE2 has always had a solid, but simple way of dealing with risk. With the latest version, released in June, a number of excellent ideas and concepts have been introduced. Here are the best seven:

Step 1: Having a Risk Management Strategy

In my experience risk management is something that is talked about a lot but rarely done. One problem is that people don't know who should be doing what. To help with this PRINCE2 2009 introduces a Risk Management Strategy. It outlines the way in which risk will be identified, evaluated and dealt with in a project. It shows who should be responsible for carrying out the various risk management roles. It also sets out how much risk an organisation is willing to bear. The strategy is put together at the outset of the project; everyone reviews and signs up to it.

Step 2: Risk Identification Techniques

Where do you start when it comes to identifying all the potential risks in your project? The new manual gives a number of approaches. These include reviewing lessons learned from previous projects, carrying out a risk brainstorming session, using an industry specific prompt list showing likely areas of risk or creating a risk breakdown structure. The latter is a hierarchical diagram like an organisation chart. It can be sub-divided in a range of ways, for example by product, by team or using PESTLE (political risks, economic risks, social risk, technological risks, legal risks, environmental risks). It can be used as a focal point for a workshop to identify all risks in each area of the project.

Step 3: Early Warning Indicators

It is all too easy for a project manager to myopically focus on a small set of performance areas such as work completed to schedule. The new manual suggests a range of other early warning indicators that identify how the project is performing. For example percentage of approvals accomplished, number of issues being raised and number of defects being captured in quality inspections. Reviewing all aspects of a project increases the likelihood of identifying more critical risks.

Step 4: Assessing the Overall Risk Exposure

PRINCE2 2009 gives an approach to show the overall risk situation of a project. Each risk is given a likelihood in percentage terms and an impact should it occur in monetary terms. By multiplying one by the other an expected value can be calculated. Totalling the expected values of all the risks gives a monetary figure that easily shows the exposure of the whole project to risk.

Step 5: Considering the Effect of Time on a Risk

PRINCE2 has always recommended recording when each risk will occur. It calls this the proximity of the risk. But in this latest release it gives examples of how you might categorise proximity, such as imminent, in the next stage of the project or after the project. It also recommends considering whether the probability of the risk occurring and/or the impact on the project if they do occur, might vary over time. Having this information can help focus on risks that are of a more pressing concern.

Step 6: Giving a Clearer Approach to Help Define Risks

Rather than just thinking about the event that may or may not occur such as a road collapsing underneath a heavy load, the new manual considers what could cause the event. This allows for a deeper analysis of any individual risk. If the road collapses it could be caused by heavy rain, bad driving or initial poor construction of the road by the council. Understanding what are the most likely causes for each potential risk event, can help implement better mitigation plans to deal with them.

Step 7: Focus on Opportunities

Risks can be opportunities. For example a new technology might appear to speed the programming of a software module. PRINCE2 2009 gives three ways of approaching an opportunity: exploit it by doing something that ensures it occurs, increase the probability or impact of the event occurring or simply reject the opportunity. In practice a good project manager is always looking for opportunities to improve their project, but making this explicitly part of the risk management process, improves the probability of spotting more.


David Hinde is a recognised expert in management development and executive coaching in the UK. He founded Orgtopia in 2003 and since has helped many organisations such as the BBC, Citigroup and the British Army to develop and unlock their leadership and management potential.


Comments

Be the first to comment on this article.

Add a comment



(never displayed)



 
2000
Enter the word hand backwards.
Notify me of new comments via email.
Remember my form inputs on this computer.

Reducing Your Cost of Quality

100% quality stamp

The cost of quality is a significant cost on any project so prudent managers look for ways to keep those costs in check.

Root Cause Analysis

Word cloud for Root Cause Analysis

The Root Cause Analysis method, when used properly, gives the project manager the ability to diagnose a problem that negatively impacted the project and remove it when it is first noticed.

SWOT Analysis in Project Management

Colourful SWOT analysis diagram in shape of leaves

SWOT Analysis is one of a number of different techniques used by professional project managers to help with decision-making.

Using Feedback as a Tool

Feedback blue round grungy vintage rubber stamp

Using feedback as a tool can help to motivate people, help with a persons development, uncover risks and issues and solve problems.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Lijoy commented on…
A Brief History of Project Management | Project Smart
- Fri 20 January 7:16pm

Kelly D commented on…
Managing Small Projects
- Thu 19 January 4:45pm

Sean H commented on…
Better Coaching Using the GROW Model
- Thu 19 January 3:43pm

Latest tweets

Managing Small Projects https://t.co/kLmCdOgGMJ An excellent summary of basic project management. #projectsmart #pmot #pm about 1 day ago

General Project Management • Newbie needing some advice https://t.co/R3kO7SHsUv #projectsmart #pmot about 2 days ago

General Project Management • Re: Junior PM needs advice - potentially being moved to a project… https://t.co/vJMX8Atrw1 #projectsmart #pmot about 7 days ago