Project Smart ~ Exploring trends and developments in project management today

Calendar iconNot recorded
Adobe PDF icon

3 Main Benefits of Project Baselining

~ By Linda Russell

Time is money blue vintage stamp

When you have finished planning your project, and you have all the scheduled dates, hours, and costs (and charges if applicable) agreed, why is it a good idea to store these values? We explore the reasons.

What is a Baseline?

A baseline is a set of stored values. Usually, these will be:

  • Original Scheduled Start and Finish Dates
  • Planned Effort (may be expressed in hours)
  • Planned or Budgeted Cost
  • Planned or Budgeted Revenue

Why Baseline?

The main benefits of having a project baseline are:

  • Ability to assess performance
  • Earned Value calculation
  • Improved future estimating accuracy

Assessing Performance

If you know what the plan was, you can compare this with the actuals, and make a judgement on whether you're on track or not. Your software may have a "traffic light" or similar system to indicate this. This provides you with variance information which can be useful for future estimating.

For instance, a task was planned to start last week and the planned effort/duration was ten days. It should, therefore, finish at the end of this week. It is now Monday of week 2. The task started last Wednesday and, having reviewed the task, you now estimate that it will take another eight days to complete it.

Planned Start Monday Week 1Actual Start Wednesday Week 1
Planned Finish Friday Week 2 Scheduled Finish Wednesday Week 3
Planned Duration 10 daysRevised Duration 11 days

Hence, on current estimates, the task will take an extra day to complete and will be three days late.

This is a somewhat crude way of assessing how well you're doing. If you add a value for progress (percentage complete), a better measure is to use Earned Value. If you record the actual hours spent on the task, your software may be able to calculate the percentage complete value.

Earned Value

With Earned Value, you compare the planned hours and costs of work with the actual hours and costs, taking into account the progress on each task and the project as a whole. It often includes the calculation of a performance indicator.

This allows you to see trends in performance, and thus to predict potential overruns. At an individual task level, it is a good indicator of how much time and cost should have been spent so far, compared to how much time and cost has been spent.

However, it is advisable not to place too much reliance on such forecasts, especially in the early stages of the project's lifecycle, as few tasks have been started or completed; as time moves forward, the accuracy of the predictions increases, although you are still reliant on peoples' assessments of progress.

When a task is completed, the Earned Value figures will be equal to the planned figures, so this measure cannot be used to enhance estimating accuracy.

Improved Estimating

When you create your plan, you estimate how long each task will take, and how much effort will be required to complete it. You may also work out the likely costs and if you're charging for work done, what the revenue will be. How do you do this? The tools most commonly used are previous experience - plus a device such as a crystal ball!

You can improve the accuracy of your estimating if you have a record of previous estimates compared with the actual outcome. This can give you a margin of error (perhaps as a percentage) which you can build into all future estimates.

If your project management software has a template facility, at the end of each project you can use the variance data to update the template tasks with revised estimates.

Conclusion

Having a baseline for each project allows you to monitor current project performance and also to improve the accuracy of future estimates.


Linda Russell has an M.A. (with Distinction) in Technical Authorship, and over 25 years' experience in software implementation and consultancy.


Comments

Be the first to comment on this article.

Add a comment



(never displayed)



 
2000
What is the month after February?
Notify me of new comments via email.
Remember my form inputs on this computer.

So You Want to Be a Project Manager

Businessman smiling with hands together

Not sure what skills it takes to become a Project Manager? This article lists the six key skills required to be a successful project manager.

Work Breakdown Structure Made Easy

Work Breakdown Structure

The Work Breakdown Structure is a deliverable-oriented, hierarchical decomposition of the work to be completed by a project team.

How to Get the Most From Your Project Team

Project team in a huddle

Project management is people management. Here's our reminder of how to make sure you get the most from your project team.

Estimating Project Costs

Money and a calculator

Tips and advice for estimating project costs, including three point estimating and Monte Carlo Simulation in MS Excel.

PROJECT SMART is the project management resource that helps managers at all levels improve their performance. We provide an important knowledge base for those involved in managing projects of all kinds. With weekly exclusive updates, we keep you in touch with the latest project management thinking.

WE ARE CONNECTED ~ Follow us on social media to get regular updates and opinion on what's happening in the world of project management.


Latest Comments

Christee commented on…
The Role of the Project Manager
- Wed 6 June 7:33am

Jennifer commented on…
Introduction to Project Management
- Tue 22 May 3:51pm

Kelsey commented on…
How to Create a Gantt Chart Using Microsoft Excel
- Wed 9 May 3:41pm

Latest tweets

General Project Management • Project Management Software/Program https://t.co/P0i0pHFnK4 about 1 month ago

General Project Management • Re: Identification System for Project Management Methodology https://t.co/NFpZ4re9ix about 1 month ago

General Project Management • Re: Project Management Interview With Presentation https://t.co/UEmX0YxHLq about 1 month ago