Work Breakdown Structure: Purpose, Process and Pitfalls

By Micah Mathis, PMP
Post-It Note Work Breakdown Structure (WBS)

In this article we are going to look at what many project managers and project management professionals refer to as the "foundation" of the project, or at least the foundation of project planning. The Work Breakdown Structure (WBS) is defined by A Guide to the Project Management Body of Knowledge 3rd Edition (PMBOK Guide) as:

"A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables."

Wow! That is a lot of buzz words and jargon, but do not worry. It is not nearly as daunting as it sounds. Creating a quality WBS will require a substantial amount of energy, time, and people, but in the end is not rocket science. However, before we get too deep into how to actually create a WBS let's first look at its purpose.

Purpose

Why do we need to create a WBS for our projects? What purpose does it serve? Why should I waste my time writing on post-it notes and drawing charts when I could be getting my team started on the actual work of the project? Now, I know everyone reading this is a great project manager or team member, so I am sure none of you have ever said comments such as these, but I am sure you have heard them from those "other" project managers who will remain nameless.

So to answer these questions, let's take a look at what purpose the WBS serves to our project and our project team. There are three reasons to use a WBS in your projects. The first is that is helps more accurately and specifically define and organise the scope of the total project. The most common way this is done is by using a hierarchical tree structure. Each level of this structure breaks the project deliverables or objectives down to more specific and measurable chunks. The second reason for using a WBS in your projects is to help with assigning responsibilities, resource allocation, monitoring the project, and controlling the project. The WBS makes the deliverables more precise and concrete so that the project team knows exactly what has to be accomplished within each deliverable. This also allows for better estimating of cost, risk, and time because you can work from the smaller tasks back up to the level of the entire project. Finally, it allows you double check all the deliverables' specifics with the stakeholders and make sure there is nothing missing or overlapping.

Process

Now that we have agreed that creating a WBS will be help to our project's efficiency and effectiveness, how do we go about it? First, let's look at what all we need to get started. There are several inputs you will need to get you off on the right foot:

  • The Project Scope Statement
  • The Project Scope Management Plan
  • Organisational Process Assets
  • Approved Change Requests - (PMBOK Guide)

These inputs should give you all the information you and your team needs to create your WBS. Along with these inputs, you will use certain tools as well:

  • Work Breakdown Structure Templates
  • Decomposition - (PMBOK Guide)

Finally, using these inputs and tools you will create the following outputs:

  • Work Breakdown Structure
  • WBS Dictionary
  • Scope Baseline
  • Project Scope Statement (updates)
  • Project Scope Management Plan (updates)
  • Requested Changes - (PMBOK Guide)

The first step to creating your WBS is to get all your team, and possibly key stakeholders, together in one room. Although your team is not listed as an input or tool in the above sections, they are probably your most vital asset to this process. Your team possesses all the expertise, experience, and creative thinking that will be needed to get down to the specifics of each deliverable. Next, we have to get the first two levels setup. The first level is the project title, and the second level is made up of all the deliverables for the project. At this stage it is important to function under the 100% Rule. This rule basically states that the WBS (specifically the first two levels) includes 100% of all the work defined in the project scope statement and management plan. Also, it must capture 100% of all the deliverables for the project including internal, external, and interim. In reality the WBS usually only captures between 90-95%, and 100% is our goal.

Once we have gotten the first two levels set, it is time to launch into our decomposition. Decomposition is the act of breaking down deliverables in to successively smaller chunks of work to be completed in order to achieve a level of work that can be both realistically managed by the project manager and completed within a given time frame by one or more team members. This level of breakdown and detail is called the work package. Work packages are the lowest level of the WBS and are pieces of work that are specifically assigned to one person or one team of people to be completed. This is also the level at which the project manager has to monitor all project work. Now the million dollar question is how specific and small does a chunk of work need to be to still be considered a work package? Well PMBOK does not seem to give a definitive answer on that. Most project managers concur that this varies by project, but can usually be measured using the 8/80 Rule. The 8/80 Rule says that no work package should be less than 8 hours or greater than 80 hours. Notice we said that the work package is the lowest level of the WBS. Activities and tasks are not included in the WBS. They will be planned from the work packages once they are assigned.

Now you are ready to start your team on the work of decomposition, but do not get too far ahead of yourself quite yet. As grandpa always said "There is no reason to reinvent the wheel." Occasionally, you will run into a project that is a "first of its kind," but that is not usually the case. Most of the time, you, your team, or your organisation has done a project like this one in the past. That means that there should be a WBS from the previous project that you can use as a template. This will save you a lot time and effort. Even if you have not done a project like this one before, most Project Management Offices (PMOs) have basic WBS templates that can get you started. Another great technique to make your life easier is the Post-It Note Technique. I know it sounds a little cheesy, but it actually works very well. In this technique you simply write each deliverable on a post-it note and stick them at the top of a wall. Then you and your team start to break down each deliverable into components and write each component on its own post-it note. This way, as you place them on the wall and start to create your tree structure, everyone can easily see what has been accomplished and where you are headed. Also this technique allows for easy movement of components around within the WBS.

Now the conference room wall is covered in post-it notes and Sally is frantically wanting to write everything down before they start to fall, but wait one more step before you put it into an official (or semi-official) document. You can use your newly created WBS to look for missing or overlapping pieces of each deliverable. This will help eliminate change requests and double work down the road. Once that is completed, put your WBS on paper and log it into your project.

Many projects will also find it necessary to create a WBS Dictionary to accompany their WBS. The WBS Dictionary is simply a document that describes each component in the WBS. This helps clarify any specifics later on when team members completing the work or stakeholders viewing the deliverables have questions. Also, when creating the WBS for very large, lengthy, or complex projects, all the deliverables' specifics might not be known up front and, therefore, it is difficult to create a full WBS. In cases such as these many people use what is called Rolling Wave Planning. This is when you plan down to the level of detail currently known and go back to plan deeper once more information is acquired. Usually rolling wave planning needs to stay as least 2-3 months ahead of the actual work being done, but of course this varies slightly by industry.

Pitfalls

Lastly let's look at five common pitfalls to creating a WBS. If you can keep these few possible issues in mind when you are creating your WBS, you and your team will be much more successful at creating a useful and accurate Work Breakdown Structure.

1. Level of Work Package Detail

When deciding how specific and detailed to make your work packages, you must be careful to not get too detailed. This will lead to the project manager to have to micromanage the project and eventually slow down project progress. On the other hand, work packages whose details are too broad or large become impossible for the project manager to manage as a whole.

2. Deliverables Not Activities or Tasks

The WBS should contain a list of broken down deliverables. In other words, what the customer/stakeholder will get when the project is complete. It is NOT a list of specific activities and tasks used to accomplish the deliverables. How the work is completed (tasks and activities) can vary and change throughout the project, but deliverables cannot without a change request, so you do not want to list activities and tasks in the WBS.

3. WBS is not a Plan or Schedule

The WBS cannot be used as a replacement for the project plan or schedule. A WBS is not required to be created in any type of order or sequence. It is simply a visual breakdown of deliverables.

4. WBS Updates Require Change Control

The WBS is a formal project document, and any changes to it require the use of the project change control process. Any changes to the WBS change the deliverables and, therefore, the scope of the project. This is an important point to help control scope creep.

5. WBS is not an Organisational Hierarchy

The WBS and Organisational Hierarchy chart are never the same thing. Although often similar in appearance, these two documents are very different. The Organisational Hierarchy shows things like chain of command and lines of communication, but the WBS is restricted simply to a project and shows only the deliverables and scope of that project.

We hope that this article has helped you better understand the Work Breakdown Structure's purpose, process, and common pitfalls. The WBS is an extremely valuable tool to the project management methodology. It can make or break a project. It sets the foundation for the rest of the project planning. A solid WBS helps ensure proper project baselines, estimating, resource use, scheduling, risk analysis, and procurement.

Micah Mathis holds a Masters Degree in Instructional Technology and is a certified PMI Project Management Professional. He is currently the VP of Sales and Customer Relations for the Mathis Group. With the Mathis Group, he trains commercial and government organisations in Project Management Methodology and manages PMI Expert.com External Link an online project management resource. For more information on Micah Mathis or the Mathis Group please visit www.pmiexpert.com External Link. Have a question or comment for Micah? Please contact him via the website above.

Comments page 1 of 1
Click here to add a comment
Josh Nankivel
Posted 100 days ago
Cris is wrong, and he's making one of the top 7 WBS mistakes by saying the WBS should include tasks. (I define activities as service-based deliverables, but that's just a terminology difference)

I wanted to also point out that the 100% rule doesn't only mean that the WBS contains all of your project scope; it also deals with individual WBS elements, and that child elements add up to exactly 100% of the parent element.

I produced an entire training course on the proper use of the WBS if anyone is interested in learning more. It's at WBSCoach.com
Víctor Cardozo
Posted 106 days ago
Cris, I understand that what Micah is trying to say is that WBS does not have all the detail included in the Schedule (which is created later).

It is clear that WBS must include all the scope and nothing else but the scope, but it is not a list of specific activities - it only reaches down the level of work package.

VĂ­ctor Cardozo, PMP
Edward Steedman
Posted 111 days ago
Nice work mate. But to be fair, there are a couple of mistakes. Overall though, i found your post very useful. Cheers man
Rika
Posted 143 days ago
I just want to make an overview from the last comment from Cris
I think the meaning of "Deliverables Not Activities or Tasks" just as forward explanation from the point one "Level of Work Package Detail" because the list of specific activities and tasks have been united in work package as the lowest level in WBS to reduce "the complicated" because one of primary objective of WBS for making our project in simple ways to get the best understanding.

thanks
Rika
Cris
Posted 218 days ago
Hi Mathis,

Sorry mate but in the "Pitfall" section under "Deliverables Not Activities or Tasks" you said: "It is NOT a list of specific activities and tasks used to accomplish the deliverables" but this exactly what WBS is. It's a collection of "verbs" which define the main activities to be completed in order to achieve the expected deliverables. All those actions sit under each corresponding section in WBS.
And section 3 is totally wrong as well.
To be exact in PMBOK 3rd edition page 114 you can see the WBS Sample. Under each Deliverable is another subsection which is called "Work Package"; the "work Package" contains all the ACTIONS to make in order to achieve the desired outcome.

Cheers,
Cris
Senior PM
RAJKUMAR
Posted 224 days ago
which companies are using WBS in BPO
JockMcPlop
Posted 225 days ago
Are you not confusing product breakdown structure and work breakdown structure. WBS is a hierarchical breakdown of the work ina project and can be mapped to a DBS which is a hierarchical break down of the products which will be created through completion of the tasks.

Pitfall 2 and 3.

Check out J. Rodney Turner
bimal
Posted 294 days ago
You have done quite good in explaining WBS .
I have now got a good understanding of the WBS.
I would say that the bast part was the pitfall explanation.
It would have been better if you provided a structure/diagram of the WBS.
THANK YOU.
Donna M
Posted 306 days ago
Hello Mathis,
Your article is very clear and has made the information that I found so very confusing, much more understandable.
thanks a lot.
Susan York
Posted 616 days ago
Hello Mathis,
I have loooked up a couple of articles on WBS and yours has all that i needed to know in the clearest terms.
The article has indeed cleared all my earlier confusion.
Thanks a bundle
Chetan G.R
Posted 659 days ago
Hi Mathis,
I had a different view on WBS, the above article provided me the clear information on WBS.
I have noticed most of the members are still using/considering WBS for activities breakdown.
Thanks a lot for the useful and informative article.
Regards,
Chetan G.R
 

Article Categories

Related Articles

Gantt Charts, PERT Charts: What Use Are They?
Gantt charts and PERT charts are useful tools for visualising and communicating information about projects, but they have a number of limitations. In addition, the ease with which they can be created using software applications makes them open to misuse and misinterpretation.

Planning a Project using a Work Breakdown Structure and Logic Network
Projects don't just happen they are planned. The whole project team should develop the plan not just the project manager. This ensures that the teams' experiences are taken into account and that everyone is fully committed and has ownership of the plan.

Creating a Work Breakdown Structure (WBS)
The successful implementation of any Six Sigma project depends on the ability of Six Sigma professionals such as black belts to break down a large project into smaller manageable sub-projects. This breaking down of mammoth projects into several smaller projects is technically referred to as work-breakdown structure (WBS).

How to Create a Gantt Chart Using Microsoft Excel
Since the initial introduction of Gantt charts, they have become an industry standard as a key project management tool for showing the phases, tasks and activities that are scheduled as part of a project over time. This video presentation shows a step by step guide to creating a Gantt chart using Microsoft Excel 2007.

21 Ways to Excel at Project Management
The popular project management e-book now fully updated and available as a website for the first time.