Exploring trends and developments
in project management today.

Project Smart Logo

What is Earned Value?

By Duncan Haughey, PMP
Time is Money

Current performance is the best indicator of future performance, and therefore using trend data, it is possible to forecast cost or schedule overruns at an early stage in a project. The most comprehensive trend analysis technique is the Earned Value method.

In a nutshell, Earned Value is an approach where you monitor the project plan, actual work, and work-completed value to see if a project is on track. Earned Value shows how much of the budget and time should have been spent, with regard to the amount of work done so far.

Here are five other definitions:

  1. Englert and Associates, Inc define it as, "A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned."
  2. Project Magazine defines it as, "A methodology used to measure and communicate the real physical progress of a project taking into account the work complete, the time taken and the costs incurred to complete that work."
  3. The user guide for Microsoft Project 2003 defines Earned Value as, "A method for measuring project performance. It indicates how much of the budget should have been spent, in view of the amount of work done so far and the baseline cost for the task, assignment, or resources."
  4. Field Operative defines it as, "The physical work accomplished plus the authorised budget for this work. The sum of the approved cost estimates, (which may include overhead allocation), for activities, (or portions of activities), completed during a given period, usually project-to-date."
  5. NASA defines it as, "An integrated management control system for assessing, understanding and quantifying what a contractor or field activity is achieving with program dollars. EVM provides project management with objective, accurate and timely data for effective decision making."

Earned Value differs from the usual budget verses actual costs incurred model, in that it requires the cost of work in progress to be quantified. This allows the project manager to compare how much work has been completed, against how much he expected to be completed at a given point.

The project manager needs to agree the project scope, create a Work Breakdown Structure ¹ (WBS) and assign budget to each work package ², the lowest level of the WBS. Next he or she will create a schedule showing the calendar time it will take to complete the work. This overall plan is baselined (this is the planned value) and used to measure performance throughout the project. As each work package is completed (earned) it is compared with planned value, showing the work achieved against plan. A variance to the plan is recorded as a time or schedule deviation.

It is necessary to get the actual costs incurred for the project from the organisations' accounting system. This cost is compared with the earned value to show an overrun or under run.

Earned Value provides the project manager with an objective way of measuring performance and predicting future outcomes. This can enable him or her to report progress with greater confidence and highlight any overrun earlier. This in turn, enables the management team to make cost and time allocation decisions earlier than would otherwise be the case.

It is true that past performance is a good indicator of future performance. Earned Value is a useful tool for predicting the outcome of projects in terms of time to completion, cost to completion and expected final costs.

Earned Value is also known as Performance Measurement, Management by Objectives, Budgeted Cost of Work Performed and Cost Schedule Control Systems.

Definitions

  1. A Work Breakdown Structure (WBS) is a hierarchical structure used to organise tasks for reporting schedules and tracking costs.
  2. Work Packages are a small-defined set of tasks or activities that form part of an overall project scope, usually the lowest level of the Work Breakdown Structure.
Comments page 1 of 1
Click here to add a comment
James
Posted 148 days ago
Deedee you a correct if your work pacage does not have a budget you will have nothing to support your WBS.

Yuda you might be best to ask your sub to submit a schedule of valves
deedee
Posted 196 days ago
i'm trying to support the philosophy (by rule or whatever) that a work package NEEDS to have budget associated with it. wheather the budget comes from new change requests or from planning packages or a summary level WP. can someone tell me 1) am i correct, 2) what rule/industry standard can i point to that supports my philosophy?????
yuda
Posted 202 days ago
HI all, I had some problems, how to track sub contractor in our schedule, but there is no information about labor and material, only lump sump price, it is mean BCWP=ACWP? there will be CV=1? because the contract price is fixed..can you help me out?
babak
Posted 216 days ago
it is a very good article but it just introduces earned value technique . If you can share some more expert essays that describe practical use of earned value in real projects or at least in simulated samples, i will appreciate you to share you knowledge with us and upload it here preferably with calculation and formulas functionality

thanks a lot
Jai Shankar
Posted 331 days ago
I am preparing for PMP exam. It is rally very good article. Now I have very clear understanding of EV, PV and AC.
Please send me some more article to sjai99@gmail.com.

Really big thanks to you.
Author on Proj Mgmt Book
Posted 342 days ago
I always mistrust the value concept that cannot be explained in "plain English" - so this is appreciated!

I would add that in order to be robust WBS, it must include some additional key addendums at a minimum - an associated project scope definition, staffing associated with the work packages (it may take a junior person longer than a senior for the same work), critical path analysis, and risk analysis and monitoring.
Associate Professor Hamilton
Posted 426 days ago
I teach a project management course at DeVry University. This article explains the concept in very simple but thorough terms. My DBA research area explores companies that are growing. In that persuit of knowledge I am very interested in the management structures of agile companies, so the "agile project management" category is also of interest. Thanks for sharing.
Alicadius-Nairobi Kenya
Posted 429 days ago
Good notes keep it up
Santosh
Posted 551 days ago
Hi Duncan,

Good Article.

As i am Preparing for PMP can you Please share with me some Good documents.(c.as.santosh@gmail.com)
Caroline Odhiambo
Posted 745 days ago
Thanks quite helpful information for me to train aspiring project managers here in Kenya.
Helpful PMP
Posted 846 days ago
Duncan, thank you!
For good article and permission! :)

Author of HelpfulPMP
http://sites.google.com/site/helpfulpmp/
Duncan
Posted 847 days ago
Hi there, yes you can publish this article on your blog in Russian, with the appropriate attribution.
HelpfulPMP
Posted 847 days ago
Hi Duncan!
Thank oyu for clear EV explanation!
Please let me know if i can translate to Russian and put to my blog part/all of your article, keep reference to this page?
 

Article Categories

Related Articles

How to Implement Earned Value
Earned value (EV) is one of the most sophisticated and accurate methods for measuring and controlling project schedules and budgets. Earned value has been used extensively in large projects, especially in government projects. PMI is a strong supporter of the earned value approach because of its ability to accurately monitor the schedule and cost variances for complex projects.

PDF Icon Earned Value, Clear and Simple
The term "Earned Value" is gaining in popularity around project management circles as if it is some wonderful new concept to be embraced. Yet, it has been in use since the 1960s when the Department of Defence adopted it as a standard method of measuring project performance. Today, it is both embraced and shunned, often in response to prior experience or stories told "in the hallway." The opponents will generally cite the cost and effort to make it work, and the limited benefit derived from its implementation. The proponents will cite the cost savings to the project overall, the improved analysis, communication and control derived from its implementation. No doubt, the two camps have vastly different experiences to formulate their perceptions.

Earned Value Management Explained
Earned Value Management (EVM) helps project managers to measure project performance. It is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project forecasting. The project baseline is an essential component of EVM and serves as a reference point for all EVM related activities. EVM provides quantitative data for project decision making.

The Secrets to Earned Value Management Success
Earned Value (EV) is a management tool for tracking and communicating a project's status. Earned Value Management (EVM) will let you know the actual state of the project by comparing your current project performance against your plan. Knowing the project's performance will let you take actions needed to ensure that the project is completed on time and within budget. Like any tool, in order for EVM to be successful, it very important that it is used correctly.

21 Ways to Excel at Project Management
The popular project management eBook now fully updated and available as a website for the first time.