The "Real" Project Plan
2009
"I need a project plan by tomorrow morning." As project managers, that's what we hear. But we know that what the boss usually means is that s/he wants a project schedule. There is a problem though, how can you come up with a schedule without having the "real" project plan first?
The project plan, or project management plan as defined by PMI (for simplicity, we'll call it project plan in this article), is completely different from a project schedule and is the result of the planning processes. A change in the project plan can affect the project schedule. The project plan describes how the project work will be performed. It is the primary source of information for how the project will be planned, executed, monitored, controlled and closed.
The development of the project plan is an iterative process in itself. It is composed of a single document or a master document with a series of subsidiary documents, each defining one or several areas of the project management process.
The project plan content varies based on the project scope and complexity of the project. PMI says that the plan includes:
- The project management processes selected by the project management team.
- The level of implementation of each selected process.
- The descriptions of the tools and techniques to be used for accomplishing those processes.
- How the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes, and the essential inputs and outputs.
- How work will be executed to accomplish the project objectives.
- How changes will be monitored and controlled.
- How configuration management will be performed.
- How integrity of the performance measurement baselines will be determined and used.
- The need and techniques for communicating among stakeholders.
- The selected project life cycle and, for multi-phase projects, the associated project phases.
- Key management reviews for content, extent, and timing to facilitate addressing open issues and pending decisions.
A subsidiary plan may include but is not limited to:
- Project scope management plan.
- Schedule management plan.
- Cost management plan.
- Quality management plan.
- Process improvement plan.
- Staffing management plan.
- Communication management plan.
- Risk management plan.
- Procurement management plan.
The plan may include these other components, once they are known, in a subsequent iteration, but is not limited to:
- A milestone list.
- A resource calendar.
- A schedule baseline.
- A cost baseline.
- A quality baseline.
- A risk register.
A project plan is not a one-time deliverable that remains static throughout the project. Updates arising from approved changes during project execution may significantly impact parts of the plan. The project plan must be kept in sync with approved changes and this is an iterative and ongoing process called rolling wave planning and the results of these iterations are documented as updates to the project plan.
Now that we know what a "real" project plan is, it is time your boss does too. Don't you think so...? Well, I do.
Jorge Dominguez wrote the article "The "Real" Project Plan" and recommends you visit www.Expiriance.com
for more information about project management.
Related Articles
Project Planning A Step by Step Guide
The key to a successful project is in the planning. Creating a project plan is the first thing you should do when undertaking any kind of project. Often project planning is ignored in favour of getting on with the work. However, many people fail to realise the value of a project plan in saving time, money and many problems.
Critical Path Mapping
The activity network diagram is a method of displaying the timelines of all the various sub-tasks that are involved in any project. By doing this, the total task duration and the earliest and latest start and finish times for each task are also calculated and displayed. In addition to showing which sub-tasks are critical to on-time task completion, the activity network diagram can help determine where extra effort to speed a sub-task will have the greatest payoff to overall speed.
Project Plans: 10 Essential Elements
A project plan is more than just a Gantt chart, but do you know what you must have in your plan? This article takes you through the 10 essential elements your project plan has to have to help you achieve project management success.
6 Steps to Successful Schedules
Creating a comprehensive schedule is one of the more difficult activities that project managers face. Schedule creation is often considered more art than science, and results often support this. What is often more frustrating is that team members often find themselves on one team with a project manager that creates and manages schedules a particular way and on another team with a project manager with a different approach.