Project Ranking: The Heart of Project Portfolio Management

By George F. Huhn
Folder with a questionmark on it

Project ranking is at the heart of project portfolio management (PPM). A good project portfolio ranking system should not only make the job much easier and faster, but also yield a superior result over doing it manually or with simple spreadsheets.

Almost every project portfolio management system comes with its own "twist" on project ranking: some are excellent, some are good, and some are poor or just wrong.

A value-maximising and clearly understandable project ranking system is an essential part of a project portfolio management system. It should be based in sound, quantitative, and modern decision-science.

Here are some key things to consider when thinking about project portfolio ranking systems:

  • Avoid systems that rank based on a financial metrics alone, such as net present value (NPV) or return on investment (ROI). The major limitation of using purely financial metrics is that it can underestimate the true value of projects (for example, time to market advantages or increased shareholder value). With NPV, higher discount rates selected to account for higher project risk can bias portfolios toward shorter-term projects with faster payoffs because longer-term projects may be overly discounted.
  • Look for systems that prioritise based on the integration of value-adding criteria into the ranking system. Systems that use multi-criteria decision analysis (MCDA) or multi-attribute utility theory (MAUT) usually do this. However, make sure you have flexibility in the type of data you can use and that you can adjust the utility or attractiveness curves to reflect your preferences.
  • Avoid systems that use the Analytic Hierarchy Process (AHP) for project ranking. AHP is one of the more popular project ranking techniques and is appealing by its seeming simplicity; however, it is not a quantitatively sound technique for ranking projects.
  • Look for systems that let you test sensitivity and understand how the portfolio changes under different scenarios. Sensitivity testing can be important in testing the robustness of your ranking. Most systems only let you rank based on a "most-likely" scenario.
  • Select a system that can handle uncertainty in the data and the ranking systems parameters. Systems that use Monte-Carlo simulations to simulate multiple portfolio scenarios automatically are ideal for this.
  • Avoid systems that rank projects based solely on pseudo-quantitative methods like "balance" or "portfolio alignment," or other non-value maximising approach. While these names may sound intuitive and appealing, most are pure snake-oil when it comes to solid project portfolio ranking. They do not create value-maximising portfolios.
  • Look for systems that have clear and understandable graphical presentations of the data, but remember that pretty charts are not a substitute for sound data analysis. If you need too many charts to explain your results then you'll likely confuse your stakeholders.
  • Choose systems that have mathematically and theoretically sound methods. Be sure that you can understand qualitatively how it works and that you can explain it to others (because you'll surely need to later!).
  • Avoid vendors that will not or cannot show you the underlying mathematics and explain to you in plain language how it maximises portfolio value.

Before you buy, try the software you have selected on a small portfolio of 12-20 real or fictional projects using metrics that you expect to be using. The application should prioritise the projects in a way that is understandable and makes sense to you. If it does not, then there may be something wrong in the underlying logic. A portfolio ranking system is an aid to good decision-making, and should reflect your values and strategies.

In summary, be sure that the underlying ranking methodology is sound and testable. Be aware of tools that use pseudo-quantitative methods for project ranking or do not offer any methodology for sensitivity testing. Make sure that you can test the tool on a small project portfolio so you can be certain you understand the results.

If you're a business professional interested in learning more about how project portfolio management applications can maximise the value of your project portfolio, be sure to visit DataMachines.com External Link to learn about Optsee, an integrated project portfolio management tool for prioritising and optimising corporate project portfolios. By automatically analysing your project portfolio in thousands of scenarios and then optimising against multiple constraints such as limited funding and resources, Optsee quickly shows you your most-likely return from an optimal portfolio.

Data Machines also offer a free spreadsheet/worksheet External Link for easily calculating the return on investment (ROI) for any project portfolio management tool.

Comments page 1 of 1
Click here to add a comment
George Huhn
Posted 809 days ago
Thanks for your comments.

Demian, I agree that many stakeholders are reluctant to use quantifiable ranking and optimization methodology. The reasons they are reluctant range from not knowing such tools exist, feeling challenged by the complexity presented by many of them, and poor or non-value-adding prior experiences with PPM tools.

In my experience, though, managers using "manual" PPM ranking and project selection are usually not satisfied with either the process or the results. Our approach has been to design a tool that gives them quantified, rigorous, and defendable project ranking and optimization that is faster and better than doing it the "manual" way.

And, yes, I agree 100% that "what happens after ranking" yields the ultimate priorities. We think that once project metrics are assigned and the projects have been ranked, selecting a portfolio from different optimized constraint scenarios is a much more strategic activity for managers than arguing about slight individual project differences.

Lee, I would gladly point out that your site, http://www.prioritysystem.com/ has probably the most comprehensive material for selecting a PPM tool available on the web and in much much more detail than I have written here. I highly recommend to anybody considering a PPM system that they bookmark your site and refer to it as they evaluate different PPM tools.

Gabriel, indeed, we have designed our flagship PPM tool Optsee® to provide these project ranking features. I'd love to hear any other ideas on additional design criteria that would improve it.
Gabriel Blanc-Laine
Posted 836 days ago
Good walk-thru of what should and shouldn’t be evaluated when looking for a solution. But might I guess that Data Machine does what you recommend to look for and doesn't do what you recommend to avoid?

Qtask.com
Lee Merkhofer
Posted 840 days ago
Hi George. Thanks for providing many of the same recommendations that I've provided in the conclusion section of my paper at http://www.prioritysystem.com/tools4.html. You might want to point out to readers that more detailed arguments for these points can be found in main body of my paper.
Regards.
Demian Entrekin
Posted 846 days ago
I agree with your assessments of using misleading quantifiable metrics, such as your concerns of NPV, etc. I am a fan of math that is simple and relevant to the decision makers.

Quantifiable ranking works best when the key stakeholders are ready, willing and able to make decisions that way. In cases where the organization does NOT think that way, you may have to use other means.

The big question I have is what happens after ranking. In my experience, the only meaningful expression of priority is the forward looking allocation of resources. That is rubber on road.

Demian Entrekin
http://it.toolbox.com/blogs/ppmtoday/
 

Article Categories

Related Articles

The Top 6 Things to Consider When Choosing a PPM Solution
According to a recent article in a leading technology magazine, the demand for project and portfolio management (PPM) solutions is rising in response to the weakened economy. Many businesses are choosing to implement PPM solutions in order to "identify which IT projects are mission critical and to help them execute those projects as efficiently as possible." These customers have also found that PPM solutions offered as software-as-a-service (SaaS) are both more affordable and easier to deploy than traditional ones.

How Often Should You Review the Project Portfolio?
You've got a ton of projects. You can't do them all at once because you don't have the people to do them. You know better than to ask people to multi-task on more than one project, no one will get anything done. One tactic is to organise the projects into a portfolio and rank them by priority.

Building the Project Firing Squad
Regardless of where your IT organisation has progressed in the evolution from a utility like service to a executor of business strategy, the bread and butter of most IT organisations is the successful execution of projects: non-recurring, limited duration activities designed around completing a defined task. As organisations have grown savvier about project management, successful execution is on the rise, however choosing the right projects to deliver remains a challenge for many companies.

PDF Icon Monte Carlo Simulation in MS Excel
The Monte Carlo method is based on the generation of multiple trials to determine the expected value of a random variable. There are a number of commercial packages that run Monte Carlo simulation; however a basic spreadsheet program (such as Microsoft Excel) can be used to run a simulation.