Planning a Project Using a Work Breakdown Structure & Logic Network
Projects don't just happen they need planning. Involve the whole project team in developing the plan, not just the project manager. This ensures team members experience is considered and each person is fully committed to, and has ownership of the plan. A good project plan provides the following:
- A road map (including clear milestones) everyone in the team can follow.
- A realistic project timescale.
- Details of resource requirements.
- Validation of the estimated cost.
- Identification of task slippage.
- Early warning of problems.
It pays to use previous experience and lessons learned from similar projects.
- How long did it take?
- How much did it cost?
- What were the problem areas?
- What were the successful areas?
Running a project without a plan is foolish. Working without knowing where you are going is likely to lead to problems and possible failure. Running a project without a plan, is like trying to find your way in a strange city without a map. As the saying has it, "If you fail to plan, you are planning to fail."
Work Breakdown Structure (WBS)
To identify the individual tasks in a project, it is useful to create a Work Breakdown Structure. The WBS is the foundation for the detailed project plan. Get the team together and brainstorm all the tasks and subtasks in the project, in no particular order. Write them down on sticky notes and put them on a whiteboard. Once everyone has thought of as many tasks as they can, arrange the sticky notes into groups under the major areas of activity. Add, change, remove and shuffle the sticky notes until the WBS is accurate, complete and logical. The purpose of a WBS is to decompose the project into steps and sub steps.
Logic Network (Time Chart)
A Logic Network shows the sequence of activities in a project across time. It shows which activity logically precedes or follows another. Create a Start (left) and End (right) sticky note and put them on the whiteboard. Arrange the WBS sticky notes in the logical sequence of activities from left to right. Join the notes with an arrow in and out; some may have more than one arrow. All connecting lines on a network enter at the left (beginning) of the activity box (sticky note) and exit at the right (ending). Lines do not enter the top or exit the bottom of the activity box. Unconnected lines are not allowed. All activities must connect to another activity, or the start or end of the project. Write the time every activity will take on each sticky note to calculate the project duration. You have created a Logic Network that will help you understand the dependencies in your project, timescale and its workflow. This technique can reveal important information that could be overlooked.
Milestones
Look for milestones in your Logic Network. A natural milestone may occur any time a series of parallel activities come together in a point. Control the project by defining a concrete deliverable for each milestone. A concrete deliverable is something you can see or touch such as a design specification, prototype, model, software module.
Using Project Management Software
The information from your WBS and Logic Network can be input into a software package such as Microsoft Project to provide a detailed plan. Enter the tasks, predecessors, resources and time estimates into the software. Once entered, the software will create the charts and graphs automatically. Don't expect the software to plan or manage the project; it's just a tool.
Checklist
Here is a checklist to help you create a well thought out, detailed project plan while building a committed high performing team.
- Define what needs to be done using a Work Breakdown Structure.
- Discover the best approach for getting everything done by developing a Logic Network.
- Develop work and duration estimates of how long each team member needs for each task.
- Calculate how long the project will take to complete its critical path and milestone schedule using the Logic Network.
- Calculate and chart the number of people needed and the percentage of each team member's time for each phase of the project.
- Adjust and refine the project plan to level individual workloads and smooth the number of people needed during the project.
- Creatively optimise trade-offs to deliver the best results in the shortest time.
- Use the joint planning process to intensify team members' commitment and ownership.
Related Articles
Work Breakdown Structure: Purpose, Process and Pitfalls
In this article we look at what many project managers and project management professionals refer to as the "foundation" of the project, or at least the foundation of project planning. The Work Breakdown Structure (WBS). Creating a quality WBS will require a substantial amount of energy, time, and people, but in the end is not rocket science.
Creating a Work Breakdown Structure (WBS)
The successful implementation of any Six Sigma project depends on the ability of Six Sigma professionals such as black belts to break down a large project into smaller manageable sub-projects. This breaking down of mammoth projects into several smaller projects is technically referred to as work-breakdown structure (WBS).
Gantt Charts, PERT Charts: What Use Are They?
Gantt charts and PERT charts are useful tools for visualising and communicating information about projects, but they have a number of limitations. In addition, the ease with which they can be created using software applications makes them open to misuse and misinterpretation.
How to Create a Gantt Chart Using Microsoft Excel
Since their first introduction, Gantt charts have become an industry standard. They are an important project management tool used for showing the phases, tasks, milestones and resources needed as part of a project. This video presentation is a step-by-step guide to creating a Gantt chart using Microsoft Excel 2007.