How Gantt Charts Can Help Avoid Disaster
Having run 15 months late on completion of a construction project, a building company incurred extensive penalty charges, which eventually led to its closure. Not having any project Gantt charts indirectly led to the company's failure.
Background
In my article "Gantt Charts, Pert Charts: What Use are They?" I said that Gantt charts are useful tools to help you manage better, but they won't give you all the answers. What I didn't say is that not having a Gantt chart can be disastrous: a company recently went into receivership, partly because it didn't have Gantt charts showing the critical paths on a major construction project.
Penalty Charges
The original contract for the construction of a block of flats did not include a dated project plan showing the critical path. When changes to the specification were made by the customer, no plan revisions could be produced to show how these changes would affect the project end date. The flats were finally ready for handover some 15 months later than the original agreed end date, leading to penalty charges.
In order to contest the penalty charges, the company needed to show:
- The handover date specified in the contract was possible within the original specification.
- That the end date was bound to slip because of the extra tasks and extended durations caused by the customer's changes.
All they had was a series of spreadsheets listing the tasks undertaken: a new spreadsheet was created when each change was made. The spreadsheets didn't show the variances from the original plan, nor what the impact of those changes was on the project dates.
How Gantt Charts Would Have Helped
If they had created a Gantt chart at the contract stage, they would have had a baseline plan against which they could monitor their progress.
When the customer requested amendments to the specification, the company could have added in the necessary extra tasks and changed the durations of the existing tasks as required: this would have clearly shown the handover date slippage. The customer could then have been called upon to sign an amendment to contract, agreeing a revised end date.
Without these tools, the company was unable to prove that the delay was not caused by their own inefficiencies, although it could be argued that trying to manage a complex construction project without using appropriate planning tools is an indication of inefficiency in itself.
Conclusion
If you are called upon to manage a project for a customer where time is of the essence, you need to use appropriate tools, such as Gantt charts, to monitor the plan and work out the impact of changed circumstances, and communicate the changes to all concerned.
Linda Russell has an M.A. (with Distinction) in Technical Authorship, and over 25 years' experience in software implementation and consultancy. She has worked on the 4c programme, project and resource management software product for nearly 10 years. Using our project management software, we can create gantt charts for you. Visit 4c - Producing a Critical Path
for details.
Related Articles
How to Create a Gantt Chart Using Microsoft Excel
A Gantt chart is a popular type of bar chart that aims to show the timing of tasks or activities as they occur over time. Although the Gantt chart did not initially indicate the relationships between activities this has become more common in current usage as both timing and interdependencies between tasks can be identified.
Project Planning A Step by Step Guide
The key to a successful project is in the planning. Creating a project plan is the first thing you should do when undertaking any kind of project. Often project planning is ignored in favour of getting on with the work. However, many people fail to realise the value of a project plan in saving time, money and many problems.
How to Plan and Schedule More Complex Projects
Gantt charts are useful tools for analysing, planning and controlling projects. When a complex or multi-task project is under way, Gantt charts assist in monitoring whether the project is on schedule, or not. If not, the Gantt chart allows you to easily identify what actions need to be taken in order to put the project back onto schedule.
Developing the Project Plan
Whether you call it a Project Plan or a Project Timeline, it is absolutely imperative that you develop and maintain a document that clearly outlines the project milestones and major activities required to implement your project.
Get Project Management Templates
Project Smart is selling project management templates and tools developed and refined in a real project environment.