Earned Value Management Explained
Earned Value Management (EVM) helps project managers to measure project performance. It is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project forecasting. The project baseline is an essential component of EVM and serves as a reference point for all EVM related activities. EVM provides quantitative data for project decision making.
EVM Rewards and Recognition
According to the NASA Headquarters Library, the first version of Earned Value Management (EVM) was developed by the Defence Department (DoD) to track its programmes during the sixties. Since 2005, EVM has been a part of general federal project risk management. Today EVM is a mandatory requirement of the US government. The Office of Management and Budget (OMB) promotes use of EVM as a preferred performance-based management system to manage software projects. EVM is also used in the private sector by companies in a variety of industries, consulting firms and educational establishments.
Some of the most well known organisations practicing EVM are:
- NASA
- Project Management Institute (PMI)
- Society of Cost Estimating and Analysis
- Defence Acquisition University
- Federal Acquisition Institute
- Acquisition Management (UK)
Based on reports of the General Accounting Office (GAO) in August 1996 a memorandum of understanding concerning common cost and schedule management for acquisitions was signed by Australia, Canada, and the United States. This gives international recognition to EVM worldwide.
The NASA Office of Chief Engineer is sponsoring an "Earned Value Management EVM Award of Excellence" to be presented at the NASA PM Challenge Conference. More information is available on the NASA Earned Value Management (EVM) Award of Excellence
site.
EVM Measures
EVM consists of the following primary and derived data elements. Each data point value is based on the time or date an EVM measure is performed on the project.
Primary Data Points
- Budget At Completion (BAC)
- Total cost of the project.
- Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)
- The amount expressed in Pounds (or hours) of work to be performed as per the schedule plan.
- PV = BAC * % of planned work.
- Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)
- The amount expressed in Pounds (or hours) on the actual worked performed.
- EV = BAC * % of Actual work
- Actual Cost of Work Performed (ACWP) / Actual Cost (AC)
- The sum of all costs (in Pounds) actually accrued for a task to date
For example say we should have completed £800 pounds of work by today. We completed £600 worth of work. The BCWP is £600. The BCWS is £800. And if we actually paid £700 then (ACWP) = £700.
Derived Data Points
Cost Forecasting:
- Estimate At Completion (EAC)
- The expected TOTAL cost required to finish complete work.
- EAC
= BAC / CPI
- = AC + ETC
- = AC + ((BAC - EV) / CPI) (typical case)
- = AC + (BAC - EV) (atypical case)
Here atypical means it is assumed that similar variances will not occur in the future.
- Estimate to complete (ETC)
- The expected cost required to finish all the REMAINING work.
- ETC
= EAC - AC
- = (BAC / CPI) - (EV/CPI)
- = (BAC - EV) / CPI
Variances:
- Cost Variances (CV)
- How much under or over budget.
- CV = EV-AC
- NEGATIVE is over budget, POSITIVE is under budget.
- Schedule Variances (SV)
- How much ahead or behind schedule.
- SV = EV-PV
- NEGATIVE is behind schedule, POSITIVE is ahead of schedule.
- Variance At Completion (VAC)
- Variance of TOTAL cost of the work and expected cost.
- VAC = BAC - EAC
Performance Indices:
- Cost Performance Index
- CPI = EV / AC
- Over (< 1) or under (> 1) budget.
- Schedule Performance Index
- SPI = EV / PV
- Ahead (> 1) or behind (< 1) schedule.
EVM Example
The best way to understand an EVM example is to solve it.
Problem: A project has a budget of £10M and schedule for 10 months. It is assumed that the total budget will be spent equally each month until the 10th month is reached. After 2 months the project manager finds that only 5% of the work is finished and a total of £1M spent.
Solution:
PV = £2M
EV = £10M * 0.05 = £0.5M
AV = £1M
CV = EV-AC = 0.5-1 = -0.5M
CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun
SV = EV-PV = 0.5-2 = -1.5 months
SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = £20M
ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M
Time to compete = (10-0.5)/0.25 = 38 Months
This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete.
EVM Benefits
EVM contributes to:
- Preventing scope creep
- Improving communication and visibility with stakeholders
- Reducing risk
- Profitability analysis
- Project forecasting
- Better accountability
- Performance tracking
EVM Tools
There are many tools available on the market to measure earned value. The most common are:
- Microsoft Office Project (http://office.microsoft.com/en-us/project.
) - Primavera Cost Manager (http://www.primavera.com.
) - PlanView MPM (http://www.Planview.com.
) - iPursuit (http://www.dekkerltd.com/evm.aspx.
) - Deltek Cobra (http://www.deltek.com.
)
Related Articles
What is Earned Value?
Current performance is the best indicator of future performance and therefore using trend data it is possible to forecast cost or schedule overruns at quite an early stage in a project. The most comprehensive trend analysis technique is the Earned Value method.
Earned Value, Clear and Simple
The term "Earned Value" is gaining in popularity around project management circles as if it is some wonderful new concept to be embraced. Yet, it has been in use since the 1960s when the Department of Defence adopted it as a standard method of measuring project performance. Today, it is both embraced and shunned, often in response to prior experience or stories told "in the hallway." The opponents will generally cite the cost and effort to make it work, and the limited benefit derived from its implementation. The proponents will cite the cost savings to the project overall, the improved analysis, communication and control derived from its implementation. No doubt, the two camps have vastly different experiences to formulate their perceptions.
How to Implement Earned Value
Earned value (EV) is one of the most sophisticated and accurate methods for measuring and controlling project schedules and budgets. Earned value has been used extensively in large projects, especially in government projects. PMI is a strong supporter of the earned value approach because of its ability to accurately monitor the schedule and cost variances for complex projects.
The Secrets to Earned Value Management Success
Earned Value (EV) is a management tool for tracking and communicating a project's status. Earned Value Management (EVM) will let you know the actual state of the project by comparing your current project performance against your plan. Knowing the project's performance will let you take actions needed to ensure that the project is completed on time and within budget. Like any tool, in order for EVM to be successful, it very important that it is used correctly.
21 Ways to Excel at Project Management
The popular project management e-book now fully updated and available as a website for the first time.

The only thing I couldn't understand is in "Time to compete", you have used $ values.. In SV also, you have said "-1.5 months" where the actual number is in $. This is a very simple example so I understand. I suppose in more complex ones (or even in this simple one ofr that matter), what you want is effort converted to cost. Is that correct?
first sorry for my english
I am interesting a lot on EVM but I read a lot too and never I found What I need like input to star my EVM, here in Mexico some people are interestin about it I try to implement it on a construction proyect but the traditional development is hard to go out, please help me look back, in the begining just befor to star EVM my e mail is ing.jafm@gmail.com TK a lot
Estimate time to completion = Original time estimate / SPI
Plugging in the values given -
Estimate time to completion = 10 months / 0.25 = 40 months