Better Risk Management With PRINCE2

By David Hinde
Red flowchart showing risk element

PRINCE2 has always had a solid, but simple way of dealing with risk. With the latest version, released in June, a number of excellent ideas and concepts have been introduced. Here are the best seven:

Step 1: Having a Risk Management Strategy

In my experience risk management is something that is talked about a lot but rarely done. One problem is that people don't know who should be doing what. To help with this PRINCE2 2009 introduces a Risk Management Strategy. It outlines the way in which risk will be identified, evaluated and dealt with in a project. It shows who should be responsible for carrying out the various risk management roles. It also sets out how much risk an organisation is willing to bear. The strategy is put together at the outset of the project; everyone reviews and signs up to it.

Step 2: Risk Identification Techniques

Where do you start when it comes to identifying all the potential risks in your project? The new manual gives a number of approaches. These include reviewing lessons learned from previous projects, carrying out a risk brainstorming session, using an industry specific prompt list showing likely areas of risk or creating a risk breakdown structure. The latter is a hierarchical diagram like an organisation chart. It can be sub-divided in a range of ways, for example by product, by team or using PESTLE (political risks, economic risks, social risk, technological risks, legal risks, environmental risks). It can be used as a focal point for a workshop to identify all risks in each area of the project.

Step 3: Early Warning Indicators

It is all too easy for a project manager to myopically focus on a small set of performance areas such as work completed to schedule. The new manual suggests a range of other early warning indicators that identify how the project is performing. For example percentage of approvals accomplished, number of issues being raised and number of defects being captured in quality inspections. Reviewing all aspects of a project increases the likelihood of identifying more critical risks.

Step 4: Assessing the Overall Risk Exposure

PRINCE2 2009 gives an approach to show the overall risk situation of a project. Each risk is given a likelihood in percentage terms and an impact should it occur in monetary terms. By multiplying one by the other an expected value can be calculated. Totalling the expected values of all the risks gives a monetary figure that easily shows the exposure of the whole project to risk.

Step 5: Considering the Effect of Time on a Risk

PRINCE2 has always recommended recording when each risk will occur. It calls this the proximity of the risk. But in this latest release it gives examples of how you might categorise proximity, such as imminent, in the next stage of the project or after the project. It also recommends considering whether the probability of the risk occurring and/or the impact on the project if they do occur, might vary over time. Having this information can help focus on risks that are of a more pressing concern.

Step 6: Giving a Clearer Approach to Help Define Risks

Rather than just thinking about the event that may or may not occur such as a road collapsing underneath a heavy load, the new manual considers what could cause the event. This allows for a deeper analysis of any individual risk. If the road collapses it could be caused by heavy rain, bad driving or initial poor construction of the road by the council. Understanding what are the most likely causes for each potential risk event, can help implement better mitigation plans to deal with them.

Step 7: Focus on Opportunities

Risks can be opportunities. For example a new technology might appear to speed the programming of a software module. PRINCE2 2009 gives three ways of approaching an opportunity: exploit it by doing something that ensures it occurs, increase the probability or impact of the event occurring or simply reject the opportunity. In practice a good project manager is always looking for opportunities to improve their project, but making this explicitly part of the risk management process, improves the probability of spotting more.

David Hinde is a recognised expert in management development and executive coaching in the UK. External Link He founded Orgtopia External Link in 2003 and since has helped many organisations such as the BBC, Citigroup and the British Army to develop and unlock their leadership and management potential.

Comments page 0 of 0
Click here to add a comment
There are currently 0 comments to display.

 

Article Categories

Related Articles

10 Golden Rules of Project Risk Management
The benefits of risk management in projects are huge. You can gain a lot of money if you deal with uncertain project events in a proactive manner. Experience shows that 10 golden rules exist to implement risk management successful in your project.

PRINCE2 Project Management Explained!
PRINCE2 project management methodology is a process-driven project management method, which contrasts with other reactive/adaptive methods, developed by Office of Government Commerce (OGC). PRINCE2 defines 45 separate sub-processes and organises these into eight processes.

The Principles of Risk Management
Every project manager and business leader needs to be aware of the practices and principles of effective risk management. Understanding how to identify and treat risks to an organisation, a programme or a project can save unnecessary difficulties later on, and will prepare managers and team members for any unavoidable incidences or issues.

Ranking Risks: Rare to Certain, Negligible to Catastrophic
Risk is a concept that denotes a potential negative impact to an asset or some characteristic of value that may arise from some present process or future event. In everyday usage, risk is often used synonymously with the probability of a known loss. Risk is measured in terms of impact and likelihood. Since risk is directly correlated to loss, it is important to be able to assess risks in one's business and to address them. Needless to say, inattention to risks can definitely affect a company's bottom line.

21 Ways to Excel at Project Management
The popular project management e-book now fully updated and available as a website for the first time.