By Jorge Dominguez, PMP
Adaptive Project Framework

Businesses all over continue to struggle implementing the PMBOK or PRINCE2 as a whole or parts of them claiming that they are too complex, too involved and take from the time it takes to produce the project deliverables. Adaptive Project Framework (APF) comes to the rescue by adapting to the ever changing business environments.

I read and re-read "Effective Project Management: Traditional, Adaptive, Extreme" by Robert K. Wysocki every time I get a chance. It is an excellent book that I always carry with me. This book dedicates a few chapters to APF.

APF is an iterative and adaptive (and I add agile) approach designed to deliver maximum business value to clients within the limits of their time and cost constraints where the always variable scope is adjusted at each iteration. The client decides what constitutes maximum business value and, at the end of each iteration, the client has an opportunity to change the direction of the project based on what was learned from all previous iterations therefore, embracing and managing change, not avoiding it.

Just five phases define APF:

1. Version Scope

  • Develop the Conditions Of Satisfaction (COS) to define what is needed and what will be done to meet that need.
  • Develop the Project Overview Statement (POS) which summarises the problem/opportunity, what will be done and how, the business value, and risks, assumptions and obstacles to success.
  • Prioritise functional requirements; this list may change but currently reflects the best information available.
  • Develop mid-level Work Breakdown Structure showing goal, major functions, and sub-functions.
  • Prioritise scope triangle (consisting of time, cost, resources, scope, and quality, customer satisfaction was left out).

2. Cycle Plan (iterative)

  • Extract from the WBS those activities that define the functionality to be built in this cycle.
  • Decompose the extracted WBS down to the task level.
  • Establish the dependencies among these tasks.
  • Partition the tasks into meaningful groups and assign teams to each group.
  • Each team develops a micro-level schedule with resource allocations for the completion of their tasks within the established cycle timeline and budget constraints.

3. Cycle Build (iterative)

  • Conduct detailed planning for producing the functionality assigned to this cycle.
  • Begin cycle work.
  • Monitor and adjust cycle build.
  • This cycle ends when its time has expired. Any functionality not completed during this cycle is reconsidered as part of the functionality in the next cycle.
  • Create a Scope Bank to record all change requests and ideas for improvements.
  • Create an Issues Log to record all problems and track the status of their resolution.

4. Client Checkpoint (iterative)

  • Client and project team perform a quality review of the functionality produced in the just completed cycle against the overall goal of maximum business value, and adjustments are made to the high-level plan and next cycle work if needed.
  • The sequence Cycle Plan / Cycle Build / Client Checkpoint is repeated until the time and cost budgets for this version have been expended.

5. Post-Version Review

  • Determine if the expected business outcome was realised.
  • Determine what was learned that can be used to improve the solution.
  • Determine what was learned that can be used to improve the effectiveness of APF.

A very simple framework that, as the book author says, is client-focused, client-driven, shows incremental results early and often, utilises continuous questioning and introspection, implement changes better and progressively, and strips out all non-value-added work. Everything the business has been looking for!

I am willing to give APF a try. Don't you think so...? Well, I do.

Jorge Dominguez wrote the article "Agile Project Management: AFP" and recommends you visit www.Expiriance.com External Link for more information about project management.

Comments page 0 of 0
Click here to add a comment
There are currently 0 comments to display.

 

Article Categories

Related Articles

What Agile Methods Mean to Your Process, People and Products
Studies show that most successful projects were those that followed agile principles, proving that model-driven methods are not always the best when it came to managing changes, fast-paced project implementation, or even meeting market demands. The concept of agile development is not new. However, many technologists still stick to the age-old notion that software development can be easily designed and the outputs predicted without giving much thought to the more dynamic factors of projects, such as communication lines, people, and change.

Which Life Cycle Is Best for Your Project?
When choosing a development life cycle, don't just trust your feelings. Decide based on factors that really matter. Which life cycle will work best for your project? This is an important strategic question because making the wrong choice could lead to disastrous results of catastrophic proportions. Think about delayed deliveries, unhappy clients, project overruns, and cancelled projects.

The Blending of Traditional and Agile Project Management
Traditional project management involves very disciplined and deliberate planning and control methods. With this approach, distinct project life cycle phases are easily recognisable. Tasks are completed one after another in an orderly sequence, requiring a significant part of the project to be planned up front. For example, in a construction project, the team needs to determine requirements, design and plan for the entire building, and not just incremental components, in order to understand the full scope of the effort.

DMAIC And Project Planning
Although it is accepted that extraordinary levels of quality improvement are possible only by a radical change in management philosophy, leading to change in organisational culture, the fact remains that the exercise of undertaking process improvement projects cannot be overlooked for actual change to occur. Projects are the bridge between two parts, comprising of planning and doing. Although apparently similar, project and planning are different in scope.

21 Ways to Excel at Project Management
The popular project management e-book now fully updated and available as a website for the first time.